Major update on delayed opening of £1.6m St Annes Pier Link road scheme - and what is likely to follow
Completion of project well behind 18 weeks forecast at start of work in February
The new-look Pier Link stretch of road in St Annes is set to open at last this week - but will be closed again for further work in a few weeks time.
Fylde Council, which commissioned £1.6m project to give the link between St Annes Square and the town’s Pier a fresh, inviting look, has revealed details of what has delayed the road’s opening with the work appearing the be finished.
The project is already well behind schedule after it was launched on February 23 with a completion target of 18 weeks but as the work continued over the summer break, the hoped-for completion was said to be late August or early September.


Then following the resurfacing last month, the council said areas of carriageway surfacing did not meet the standards it expects and would be put right at no cost to the council, causing completion to again be put back.
Now, a Fylde Council spokesperson has revealed just what the problem is - the wearing course, or top layer, of the resurfacing needs to be replaced, as it doesn’t meet the standard which would give the longevity of 20 years or more required.
So the plan is to open up the road to traffic - with its new westbound one-way priority for drivers - as it fine to use for now, but close it again for an anticipated three or four days in a few weeks’ time.


Enjoy unlimited access to local news, the latest football stories and new puzzles every day
With a digital subscription, you can see fewer ads, enjoy faster load times, and get access to exclusive newsletters and content. Click here to subscribe
“It may look ready to the naked eye but the main contractor George Cox has seen that the work by a sub-contractor wasn’t done to the required standard so will have to be done again,” said the spokesperson.
“It is safe to open the road for now but it will have to close again for three or four days for the work.
"We remain committed to delivering a Pier Link that St Annes can be proud of for many years to come.”
Meanwhile, the two zebras crossings at St Annes Promenade, also part of the Pier Link scheme, have not yet been opened for use because delivery of the required Belisha beacons has been delayed by the council spokesperson said it is hoped that will be resolved soon.