Major update from Fylde Council leader on St Annes town centre improvement projects
“Not run out of money, just continuing to invest in our community”
Fylde Council’s leader has moved to set the record straight over what she terms “some rather wild and inaccurate accusations” over finances for the ongoing £1.6m Pier Link scheme in St Annes.
Cllr Karen Buckley offered the clarification after our report that residents fear Fylde Council has ‘run out of money’ over what they perceive as late changes to the scheme to upgrade the section of road between St Annes Square and the Pier.


She has also given a projected completion date for that project and others which are currently ongoing in the town centre, at Garden Street and Orchard Road.
The Pier Link scheme, which began in February and was projected to take 18 weeks, is already substantially overdue.
Concern was expressed by residents over the financial situation after the pavement on the southern side of the road, outside Braxfield Court, was laid with Tarmac and not the Kellen paving present in other sections.
But Cllr Buckley said: “The project was tendered on the basis that the south side of the Pier Link would be finished in asphalt, with the extended north side finished in Kellen paving.
“As the project progressed, we identified a budget surplus through careful cost management and began exploring potential enhancements across the wider public realm programme, including Pier Link, Orchard Road and Garden Street.
“For Pier Link, we are able to upgrade the corner junctions with the Promenade using surplus Kellen paving and with Clifton Drive using reclaimed York stone from the Square.


Enjoy unlimited access to local news, the latest football stories and new puzzles every day
With a digital subscription, you can see fewer ads, enjoy faster load times, and get access to exclusive newsletters and content. Click here to subscribe
“On Orchard Road, in response to traders’ concerns, we are levelling up the slipped pavements which are a trip hazard and planting trees.
“On Garden Street, the contractors are laying reclaimed York stone to the area beyond The Sanctuary and also renewing the asphalt – all of which is to make the frontages to the shops and businesses safe and attractive to encourage customers.
“So, not run out of money, just continuing to invest in our community.
“The project is expected to complete by the end of August/beginning of September on Pier Link and by the end of October on the other areas.”