Essential Blackpool bridge improvement works delayed after protected pigeon nests discovered in scaffolding

The delay has affected the programme of works on Waterloo Road bridge.

Essential bridge improvement works in Blackpool have been delayed after protected pigeon nests were discovered inside scaffolding erected around the structure.

The delay has affected the programme of works on Waterloo Road bridge, where contractors have been carrying out structural repairs and repainting as part of a major scheme to strengthen the bridge and protect it for years to come.

Blackpool Council said several pigeon nests had formed within the scaffolding during the project. Under the Wildlife and Countryside Act, active bird nests are legally protected and cannot be moved while in use except under specific licensed conditions.

Essential improvement works to main bridge delayed for bizarre reason after discoveryplaceholder image
Essential improvement works to main bridge delayed for bizarre reason after discovery | Blackpool Council

Working alongside environmental protection officers and licensed specialists, the nests have now been carefully removed without harm to any birds, eggs or chicks. The council said the additional work caused delays while the correct legal process was followed to protect local wildlife.

To make up for lost time, council teams and contractors are now working nights and weekends wherever possible to complete the project as quickly and safely as they can. The bridge works are now expected to be completed by the end of July.

Seasiders Way will remain closed between Parkinson Way and Bloomfield Road until the work is finished, although Waterloo Road will remain open throughout the project.

Pigeons in Waterloo Bridge, Blackpoolplaceholder image
Pigeons in Waterloo Bridge, Blackpool | Blackpool Council
Join our new FREE WhatsApp Community today

All the latest news and top stories from across Blackpool and the Fylde coast directly to your phone.

Never miss a thing. Click here to join

The improvement scheme began in April and forms the first phase of a wider programme of works to upgrade Waterloo Road bridge, which carries Waterloo Road over Seasiders Way.

The current phase focuses on structural repairs and repainting to the lower section of the bridge. A second phase is scheduled for spring 2027 and will involve work to the upper bridge, requiring the temporary closure of Waterloo Road.

Diversions remain in place while Seasiders Way is closed, with northbound traffic routed via Parkinson Way, Waterloo Road, Lytham Road and Bloomfield Road. Southbound traffic is being diverted via Bloomfield Road, Central Drive, Waterloo Road and Parkinson Way.

The council acknowledged the delay may cause inconvenience and thanked motorists for their patience while the essential works are completed safely and in accordance with environmental legislation.