Everything you need to know about roadworks on St Annes Road, Blackpool as part of major resurfacing project
Everything you need to know.
Essential resurfacing works are due to begin on St Annes Road next week as part of a major programme of repairs designed to improve one of Blackpool's key transport routes for the long term.
From Monday, July 27, until Friday, September 4, maintenance and resurfacing works will take place on St Annes Road between Waterloo Road and Pedders Lane. The project has been planned following concerns raised by residents and will focus on carrying out long-term repairs beneath the road surface to improve its condition and durability.
The scheme will involve removing and repairing damaged sections of the carriageway, strengthening the road's base layers and resurfacing the route to create a smoother, safer and more resilient road. The improvements are intended to reduce the need for future repairs and minimise ongoing disruption for motorists.
.png?crop=3:2,smart&trim=&width=640&quality=65)

To help limit the impact on the local community, the works have been scheduled during the school summer holidays, reducing disruption to families, pupils and school-related traffic.
A southbound one-way system will be in operation for approximately six weeks to allow the works to be carried out safely. The restriction will apply between Waterloo Road and Pedders Lane, with northbound traffic diverted along clearly signed alternative routes.
Drivers travelling northbound will be directed either via Watson Road and Marton Drive or via Highfield Road, Hawes Side Lane and Waterloo Road.
At certain stages of the project, there will also be a short overnight closure between the Marton Drive/St Annes Road junction and the bridge to enable specific elements of the work to be completed safely.


All the latest news and top stories from across Blackpool and the Fylde coast directly to your phone.
Never miss a thing. Click here to join
Wherever possible, access for residents and pedestrians will be maintained throughout the programme.
The resurfacing project is aimed at addressing issues identified beneath the road surface rather than simply repairing the top layer, providing a longer-lasting solution for one of the area's busiest roads.
Motorists are being advised to allow extra time for their journeys and follow the signed diversion routes while the works are underway.
The council has thanked residents, businesses and road users for their patience during the programme, describing the works as an investment in better roads for the future. Once completed, the improvements are expected to provide a smoother and safer route while reducing the need for further maintenance in the years ahead.