Date set for long-awaited reopening of Kirkham Baths, almost five years after closure
Design team working on shaping much-missed facility for new era
Kirkham Baths has moved a key step closer to reopening - and a provisional date has been set for that long-awaited occasion.
The facility has been shut since December 2021, when vital roof works forced its closure byt Fylde Council, which owns the building in Station Road, has pledged to revive the baths under a £9.3m investment in swimming facilities there and at St Annes Pool.


Places Leisure, part of the UK's leading social enterprise Places for People, has been appointed the operator of both swimming pools and has now brought together a full team of specialist designers who are actively shaping the new scheme at Kirkham.
Fylde Council says the designers’ task is to create a modern, fully compliant pool and leisure facility - with a refurbished pool, gym and changing facilities - while honouring the historic character that makes Kirkham Baths such an important part of the town's identity.
Earlier this year, local contractor Warden Construction Ltd completed a programme of internal scaffolding, specialist asbestos removal, and a substantial strip-out of fixtures and fittings.
That work also provided high-level access to inspect the roof structure and uncovered historic elements of the building - crucial foundations for the full restoration ahead.
Over the coming months, the project will move through detailed design, further surveys, consultation and planning.
It is expected that the main construction phase will start next year, with the aim of opening the new facility to the public in 2028.


Enjoy unlimited access to local news, the latest football stories and new puzzles every day
With a digital subscription, you can see fewer ads, enjoy faster load times, and get access to exclusive newsletters and content. Click here to subscribe
A Fylde Council spokesperson said: “Given the age and condition of the building, this is a complex redevelopment that must be done carefully to protect its historic fabric while meeting today's safety and accessibility standards.
“The investment in Kirkham Baths sits alongside our wider work to secure long-term swimming provision across the borough and reflects our commitment to providing modern, high-quality leisure facilities close to where people live.
“Thank you for your patience and continued support as we deliver this major project for Kirkham and the surrounding rural communities.”
Fylde MP Andrew Snowden is delighted at the progress. He said: “The initial works are now done, including the internal scaffolding, asbestos removal, strip-out, and inspections needed to properly understand the building condition.
“This is an old building, so it needs to be done properly.
“The next step is getting the design right for a modern pool, gym and changing facilities, while keeping the character that makes Kirkham Baths special.


All the latest news direct to your inbox
“I am so pleased the first stage has been completed - onwards and upwards.”
The news on the Kirkham Baths progress comes shortly after the announcement from Fylde Council and Places Leisure that St Annes Pool and Gym is to remain closed until further notice after being shut since April for renovation works.
The decision was after engineers and contractors identified the need for additional essential works beyond the original scope.
The pool and gym had initially been expected to reopen within an eight to 12-week programme of maintenance, but the timeline has been extended, said Fylde Council, to allow for further investment and improvements to ensure the building can operate safely and effectively in the long term.