Princes Way to close for more than a month as Anchorsholme coast defence works get under way

A key road in Anchorsholme will close for more than a month as work begins on a major coastal defence project designed to protect thousands of homes from flooding.

Blackpool Council has confirmed that Princes Way will close at the junction with Queen’s Promenade from January 27 until February 28.

The closure is needed to allow the installation of construction compounds for the Anchorsholme Coast Protection Scheme.

A key road in Anchorsholme will close for more than a month as work begins on a major coastal defence projectplaceholder image
A key road in Anchorsholme will close for more than a month as work begins on a major coastal defence project | Iconic Media

The rest of Princes Way will remain open at Kingsway and Anchorsholme Lane West, with a signed diversion in place.

Pedestrian access will remain open, though some on-street parking on Princes Way will be unavailable.

A section of Cycle Route 62 will also close periodically, with diversions provided.

Preparation works for the scheme are due to begin on January 26, with two construction compounds set up near Little Bispham tram stop and along Queen’s Promenade to support the works and provide access to the beach.

The Anchorsholme Coast Protection Scheme aims to safeguard homes and businesses along Blackpool’s northern coastline, where erosion and rising sea levels pose a growing threat.

The council has warned that without action, more than 5,000 properties in and around Anchorsholme could be at risk of flooding in the future.

As part of the project, five large rock groynes will be installed on the beach to trap sand and raise beach levels, helping to absorb wave energy during storms.

A new rock revetment will also be built on top of the existing sea wall to provide stronger, long-term flood protection.

Funding of £11 million has been allocated by the Environment Agency for the groynes, while the revetment will be delivered by contractor Balfour Beatty at no cost to the council.

Main construction work on the beach and sea defences is expected to begin in May 2026 and continue through to 2028, with Princes Way expected to reopen once the compound installation is complete.

Residents are being advised to follow signed diversions and check for updates as the works progress.

News you can trust since 1873
Follow us
© 2026 Iconic Media Group Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice