Blackpool tram bosses speak for 1st time on essential repairs amid worrying derailment concern
An extension to a repair order has allowed transport chiefs to carry out essential maintenance.
Blackpool Transport bosses have spoken for the first time after being given an extension to carry out vital repairs on the resort’s trams.
Last month they reassured passengers that safety as their “top priority” after they were ordered to make urgent repairs by a transport watchdog. An examination by the Office of Rail and Road (ORR) had previously revealed the service, run by Blackpool Transport, was in contravention of Health and Safety legislation.
The report says the company had "failed to take, so far as is reasonably practicable, appropriate measures to control known risks associated with bogie degradation". Bogie degradation is where the axles of trams and trains become worn during years of use due to vibrations.

Inspector Lyndsay Pyke said some of the resort's trams could be at risk of "derailment or collision", if the problem was not fixed and Blackpool Transport were given until June 19 to carry out repairs to the Office of Rail and Road's satisfaction.
However, emerged that Blackpool Transport has been granted extra time to carry out the maintenance and now must complete the work by August 13. Blackpool Transport says much of the work involves documentation not issues affecting passenger safety.
A spokesman for Blackpool Transport said: “Safety is always our number one priority, and we have already made substantial progress on bringing our maintenance and testing documentation to the standards required by the improvement notice.
“However, we have been asked by the ORR for additional information, and we will continue to work with the regulator on further strengthening our processes and procedures.”
.png?crop=3:2,smart&trim=&width=640&quality=65)

Enjoy unlimited access to local news, the latest football stories and new puzzles every day
With a digital subscription, you can see fewer ads, enjoy faster load times, and get access to exclusive newsletters and content. Click here to subscribe
The firm must:
- Identify and fix safety risks from bogie degradation, including risks with safety-critical defects that could cause a collision or derailment.
- Carry out and document repairs before any affected trams are returned to service.
- Trams are still running on all routes, but last month a revised timetable with a slower service was introduced. The timetable changes, from May 17, were introduced to deliver a more "robust service" for passengers.
- The 15-minute Starr Gate to Fleetwood service now takes longer with additional time added to allow trams to run "more reliably".
.jpeg?crop=3:2,smart&trim=&width=640&quality=65)

All the latest news and top stories from across Blackpool and the Fylde coast directly to your phone.
Never miss a thing. Click here to join
‘Safety has always been our top priority’
Blackpool Transport said: "Working closely with the ORR, we have already made improvements to our maintenance reporting processes, primarily, the way risks and associated mitigation measures are documented.
"While the improvement notice identified shortcomings in documentation associated with some specific repairs, we would like to assure customers that safety has always been our top priority, with appropriate measures put in place to address any potential risks.
"We will also continue to work with the ORR, suppliers, industry partners and other key stakeholders to ensure trams remain one of the safest forms of public transport."
Blackpool's tramway rolling stock was manufactured by Bombardier - which is now part of Alstom - at its sites in Germany and Austria between 2010 and 2017. Alstom has emphasised the importance of regular maintenance.
A spokesman said: "We are not aware of any specific risks associated with bogies produced by us. But, in general, they are subject to continuous wear, stress and environmental exposure, and must be maintained within strict intervals to preserve safety and reliability.”