Revealed for the first time: Full list of tramway extension defects
and live on Freeview channel 276
The council said it was unable to give a complete list of "all remediation works" because its deal "requires the contractor to correct any and all defects, whether they are notified by the council or not".
It added: "This can mean that the contractor can rectify his own defects as soon as they occur, and the council is only required to notify defects that have been corrected."
Advertisement
Hide AdAdvertisement
Hide AdThe authority said the contract also means the firm overseeing the extension has to put the problems right at its own cost, so the overall £22.8m cost of the scheme remains the same.
It also scotched rumours that the tram tracks are too close together - or too far apart.
Issues that were raised - with the majority fixed - include boot prints being left in asphalt, standing water, and even a pothole.
Some work had to be re-done because it wasn't carried out properly, documents revealed, including a tram stop near Talbot Square, while the quality of paving was also called into question in places.
Advertisement
Hide AdAdvertisement
Hide AdOne of the Resilience Pathway paving stones, installed as part of an £11m mental health project, has been damaged and not yet been fixed.
And "incorrectly constructed works" led to "vehicle overrun by buses" on the traffic island outside the town hall.
John Sisk and Sons, one of the main contractors, said: "On a project of this scale and complexity, we would expect there to be a number of defects and snags as the project runs.
"The list is approaching two years old and is a rolling list used to track progress and closure. We are working closely with the Council to ensure the works are handed over in line with the specification in 2021."
Advertisement
Hide AdAdvertisement
Hide AdThe Gazette asked the council whether it was satisfied with the overall standard of the work. It said in a statement: “We will continue to manage these works with contractors to ensure that work is carried out with as little disruption as possible and completed to the required standard.”
THE LIST OF ALL FAULTS (As described by Blackpool Council)
DEFECTS LIST
Soft area of stone close to island outside the town hall
Defective concrete finish
Ponding on corner of Corporation Street and Talbot Square
Bitumen staining to kerbs
Cube strength below specified strength
Loose bollard on island outside the town hall
Damage to ducts and inspections
Damaged ducts outside Ma Kelly's
Defective surfacing in Talbot Road, Topping Street, and Dickson Road
Defective alignment of a kerb in Talbot Road
Excessive slope on The Strand
Damage to duct outside Shalimar, on the south side of Talbot Road
Damage to paintwork
Damage to Virgin Media ducts across the Promenade outside the Ibis
A gap beneath Barnfield hoarding
Defective footway surfacing adjacent to the Barnfield site
Cube strength below required strength
Advertisement
Hide AdAdvertisement
Hide AdAco channel to the rear of the north footway outside the church
Debris and detritus in all drain runs
Concrete finish
Damage to the concrete track slab on the lozenge island near the gully
HRA failures and defects
Incorrect location of the duct box in the kerb line of the central island opposite the Ibis
Loose and misaligned NAL sockets
Damage to the concrete finish in the east lay-by
Damage to the concrete finish in the east lay-by - still defective
Misaligned tactive paving at the crossing outside the Ibis
Advertisement
Hide AdAdvertisement
Hide AdMisaligned and poor quality kerb line on the north-east corner of Abingdon Street and Talbot Road adjacent to News and Booze
Lighting column left in the carriageway of the lay-by on the northern side of Talbot Road outside Heron Foods
Damaged and defective kerb lines
Defective duct runs and bends
Defective ducting between the NAL socket and the duct box at the east end of the central island in Talbot Square, opposite the Ibis
Sisk damaged newly-laid ducts adjacent to OLE30 whilst searching for other ducts
Advertisement
Hide AdAdvertisement
Hide AdNewly-laid blocks on the central island opposite the Ibis in Talbot Square failed around the circular manhole cover
Red duct laid inside orange duct at controller pillar on the north east corner of Talbot Square and the Prom outside The Counting House
ACO channel from the charity shop to News and Booze on the north side of Talbot Road. Alignment wrong and no outfall.
Incorrect location of OLE37 in respect of distance from the kerb line
Advertisement
Hide AdAdvertisement
Hide AdBlock paving at the western end of the tram stop not laid in a random pattern but in a symmetrical pattern contrary to works information
Eatern end of Tlabot Square tram stop not installed or designed in accordance with the works information
Drainage run on the lozenge island between the track and the highway not to specification or to any acceptable design
Duct run alignment
Failure of Mandrel test on Scada duct runs between duct boxes eight-nine and nine-10
Red duct leaving OLE 28 far too shallow
Orange duct inside black duct at OLE 25 to be removed
Advertisement
Hide AdAdvertisement
Hide AdTriangular island at Corporation Street/town hall needs a recessed cover in the buff tactiles, not a plain cover
Offset from the centre of the rail to the copings too great and outside guidance, design and works information at tramstop
Quality of block paving adjacent to the Counting House, Talbot Square, The Strand junction
Concrete failed to reach specified minimum strength
Poor quality flagging o nthe east side of the Prom between Queen Street and Talbot Road
Damage to Resilient paving tile
Advertisement
Hide AdAdvertisement
Hide AdCrushed drainage pipe on the eastbound carriageway in Talbot Road, near to the pedestrian crossing
Town hall uncontrolled crossing - incorrectly constructed works leading to vehicle over-run by buses
Gully outside Home Bargains not connected to the drainage system
Defective draining on the north side of the carriageway, from Home Bargains to Abingdon Street
ACO drain outside Shalimar with no outfall
Saw cut damage to rail shoulder on the Prom
Substandard footway construction outside the Ibis
Two duct failures on the Prom opposite The Strand
Mastic join between rail and HRA failing
Advertisement
Hide AdAdvertisement
Hide AdDefective cellar cover outside the community charity shop on the south side of Talbot Road
Cracks in the upper rail slab at the switches
Failure of manhole covers at various locations
HOT ROLLED ASPHALT (HRA) DEFECTS
Not a consistent straight line on joint from new to old in Dickson Road
Eastbound lane plucking (the loss of aggregate in road surface) near Wilko's
Eastbound lane showing depression (two square boot marks) near Wilko's
Bucket damage on the westbound left lane
Plucking on the westbound right lane
Plucking around iron works on the westbound right lane
Advertisement
Hide AdAdvertisement
Hide AdPlucking at the centre of the Talbot Road/Topping Street junction
Levels around the iron work on the corner of Talbot Road/Topping Street
Bitumen strip not complete at tie-in at the Dickson Road junction
Plucking between Al Amin and Othello's
Plucking between News and Booze and the Vic pub
Plucking on the north side starting at News and Booze
Plucking on the south side between the tattoo shop and the Vic pub
Advertisement
Hide AdAdvertisement
Hide AdPlucking in between the south rail at the junction with Abingdon Street
Ironworks low from Bet Sid crossing to PDSA
No bitumen strip at tie-in to existing road from News and Booze to Malloys
Surface cracks between the north rail and kerb outside Home Bargains
Plucking on the north side rail up to Talbot Express
Plucking on the south rail opposite the church phone box
Plucking opposite the left church lay-by between north and south rails
Advertisement
Hide AdAdvertisement
Hide AdOver-chipping opposite the church gate and Black Pug between the south rail and kerb
Plucking opposite the Home and HQ nightclub
Stone loss on the corner of Corporation Street and Clifton Street
Texture/finish - hump-level tolerance
Stone loss of the corner of area seven (triangular island opposite the Home and HQ nightclub)
Ponding adjacent to the bus stop on the Prom, five metres from the tie-in
Advertisement
Hide AdAdvertisement
Hide AdPlucking on the northbound carriageway, five metres from the island
Pulling/cracking next to the north/terminus bound tramline on the Prom
Pothole on the Prom
Uneven surface alongside the Ibis junction
Ponding and patchwork from the Market Street junction to the Ibis central island
Ponding and finish issue on the central/splitter island opposite the town hall
Advertisement
Hide AdAdvertisement
Hide AdPlucking at joints and no bitumen strip at joints opposite the church, between the south side rail and kerb
Pulled and boot prints at the Malloy's crossing
Cracks and pulling at the News and Booze pulling
Ponding in the loading bay outside the Vic pub
No seal at the tie-in at the junction of Talbot Road and Dickson Road
Ponding on the corner of Corporation Street
Ponding in the cycle land outside Ma Kelly's
Lighting column in Imperial lay-by
Ponding water near the Counting House
Plucking on the corner of Talbot Road and Corporation Street
Ponding water on the north side of the crossing opposite News and Booze
Ponding water on the Prom
Advertisement
Hide AdAdvertisement
Hide AdFence panel marks in the road on the corner of Talbot Road and Dickson Road
Iron works failure on the Prom opposite the Counting House
Iron works failure at the Prom/Ibis southbound junction
Ironworks failure on corner of Corporation Street/Clifton Street
Plucking on the north side of Talbot Road
Ponding water on the north Prom central island (south side)
Pondinbg water on the north Prom central island
Surface irregularity on the Barnfield temporary footpath