More disruption for rail users after line upgrade between Preston and Manchester is delayed

Rail users have been warned to expect further disruption to their journeys following a delay in completing the line upgrade between Preston and Manchester.
The company has said thattravellers can expect rail replacement buses to continue along the line at weekends.The company has said thattravellers can expect rail replacement buses to continue along the line at weekends.
The company has said thattravellers can expect rail replacement buses to continue along the line at weekends.

Network Rail advised its customers today that "poor ground conditions" have delayed the completion date for the electrification project from May to Summer 2018.

Hide Ad
Hide Ad

Travellers have been told they can expect rail replacement buses to continue along the line at weekends during this period.

The company says that progress has been hampered by unexpected running sand and hard rock in the vicinity of old uncharted shallow mine workings.

Martin Frobisher, route managing director of the London North Western Route at Network Rail, said: “While we are disappointed to miss our May 2018 target on the Manchester-Preston upgrade, it is important we view this within the full context of the Great North Rail Project.

"The ultimate prize for customers is 2020 when Network Rail’s current GNRP upgrades are fully complete.

Hide Ad
Hide Ad

“Customers in the North are already benefitting from the works - including faster, electric services between Liverpool and Manchester and from Manchester Airport to Glasgow. There is far more to come in future, including better Manchester-Preston services.”

Jerry Farquharson, service planning director for TransPennine Express, said: “It is disappointing that this complex project will now take longer to complete.

"We are working closely with Network Rail and other train operating companies to minimise disruption for our customers while the upgrade is concluded and to deliver our planned service improvements as soon as possible.”

Rob Warnes, performance and planning director at Northern, said: “This is disappointing news for our customers who will have a longer wait, with more disruption, before they can experience the service enhancements Manchester to Bolton electrification will make possible.

Hide Ad
Hide Ad

“We are committed to working with our industry partners to complete the project to its revised schedule, while doing everything we can to minimise disruption to customer journeys. We will share more detail on any changes the delayed electrification work will have on planned improvements for the May 2018 timetable change as soon as we can.”

The work Network Rail still needs to do on the Manchester-Preston scheme is the installation of foundations for steel columns to carry overhead power lines at Chorley, Bolton and Salford.

The company says that due to poor ground conditions at these locations, three out of every 10 foundations have been unsuccessful at the first attempt. This had added time to the programme.

Some 1,700 (89%) foundations are already in place at Preston, Chorley, Horwich and Bolton. But there are 200 still to put in.

Hide Ad
Hide Ad

Another challenge, which slowed the scheme’s progress, was the need to carry out emergency repairs to Moses Gate railway bridge in Bolton last year after it was damaged by a burst water main.

Network Rail’s Preston-Blackpool is progressing well and due to finish as planned by May this year.